What should you send an estimator for an accurate estimate?

Updated 13 November 2026

Send the full set of plans, the specification, every addendum, the site location and the date you need the estimate back. If the job is a tender, send the tender documents as well, so the estimator prices what the client asked for and nothing else.

An estimate is only as good as the documents behind it. A missing sheet does not make the cost go away. It just leaves it out of your price. This guide lists what to send, what each document is for, and what to do when the plans are not finished yet.

Which documents does an estimator need?

These are the documents behind most estimates, what each one is used for, and how much it matters:

Document What it is used for How much it matters
Architectural plans Floor plans, elevations, sections and details give the walls, floors, roof, doors and windows to measure Must have
Structural drawings Footings, slabs, steel and framing sizes, which drive the concrete, reo and steel quantities Must have
Specification The finishes, products and standards the plans do not show, like tile type or paint system Strongly helps
Services drawings Plumbing, electrical and mechanical layouts, if those trades are in your scope If priced
Addenda Every change issued after the first set, so nothing is priced off an old revision Must have
Tender documents The tender form, returnables, the pricing schedule and the closing date If tendering
Site location The suburb and state, because labour, materials and access are priced for the place Must have
Your deadline The date you need the estimate back, so the delivery date can be agreed before work starts Must have

Send the whole set, not just the sheets you think matter. A note on a section or a detail on the last structural sheet often changes a quantity on the floor plan.

How do you make sure the plans are the latest revision?

Check the revision letter or number in the title block of every sheet, and send the drawing register if the architect issued one. Pricing an old revision is one of the most common reasons an estimate is wrong, and it is easy to miss when sheets come in over several emails.

If an addendum arrives after you have sent the plans, send it straight through. We reprice the changes and reissue the files at no extra cost. If the overall scope changes, any change to the fee is agreed before we go on.

What if the plans are not finished?

Start with what you have. A concept set can still be measured, and the estimate will say what it could not price. Expect more of these in an early estimate:

  • Provisional sums for work that is not designed yet, like the services on a concept set.
  • PC items for fittings nobody has chosen, like tapware or appliances.
  • Questions to the designer, listed so you can chase the answers.
  • Assumptions written down, so you know which numbers will move.

That is still worth having. It tells you early whether the job fits the client's budget, and the open items show you what to ask the designer next. The questions and what sits outside the price come as lists of their own, and RFIs and exclusions in a tender explains how to use them.

Should you send your own rates?

If you have them, yes. Preferred supplier prices and subbie quotes make the estimate match what the job will really cost you. Send them with the drawings, and say which ones you want used. Estimating with your own supplier rates covers what makes a rate usable.

What else should you tell the estimator?

A few things that sit on no drawing but change the price:

  • Which trades you want priced: one trade, a few, or the whole job.
  • Anything you know about the site, like tight access, a slope or an existing building to work around.
  • Work the client is doing themselves, or items they are supplying.
  • How you want the estimate laid out, if you have a format you always use.

How do you send the plans to us?

Fill in the brief on our homepage. You can paste a shareable link to the drawings, say you will attach them to your email, or tell us they are still being prepared. Your plans stay confidential. We can sign your NDA or ours, and we do not price two competing builders on the same job.

We review the documents and come back with one fixed fee and a delivery date before any work starts. Most estimates arrive within two working days after your go-ahead, and how long an estimate takes explains what changes that. A few of the fees we have charged:

  • Granny flat, renovation, extension or shed$200 to $400
  • All trades, $2.5M house$2,000
  • 20 senior health units, NSW Health$1,100

See what a construction estimate costs for how the fee is worked out. If a word in your tender documents is new to you, the estimating glossary explains it. Find more answers in our guides.