How to price a tender from the plans
Updated 13 November 2026
To price a tender, measure every item on the plans into a bill of quantities, put a rate on every line, then add preliminaries, allowances for what is not yet known, and your margin. Send it with a list of what your price leaves out, so the client knows exactly what they are comparing.
The adding up is the easy part. The time goes into reading the documents, measuring, and finding what the drawings do not show. This guide walks through each step in order, then covers what usually goes wrong and how long it takes.
What are the steps, in order?
-
1
Read the tender documents first
Drawings, specification, addenda and the tender form. Note the closing date, what has to be returned, and anything the client wants priced a set way.
-
2
Do the take-off
Measure every item on the plans, trade by trade. Areas, lengths, volumes and counts, each one traced back to the drawing it came from.
-
3
Turn it into a bill of quantities
Set the measured items out as lines, with a unit against each one, so every line can carry a rate.
-
4
Put a rate on every line
Labour, materials and plant, from your own costs, your suppliers or your subbies' quotes.
-
5
Add preliminaries
The cost of running the job: site setup, supervision, access, cleaning and the rest. Priced for the time the job takes.
-
6
Carry what you cannot price yet
Provisional sums for work that is not designed, and prime cost items for things still to be chosen.
-
7
Write the exclusions and RFIs
What your price leaves out, and the questions the drawings did not answer.
-
8
Add your margin and check it
Overhead and profit, added once. Then check the total against what a job like this usually comes to.
Why start with the tender documents and not the plans?
Because the documents tell you what you are pricing. The specification can change a finish, a grade or a fixing that the drawing only shows as a line. An addendum can replace a sheet you already measured. The tender form may ask for the price split a certain way, or for schedules and forms to be returned with it.
Before you measure anything, check you have the latest revision of every drawing, which trades belong in your price, and what has to go back with the tender and by when. A tender that is priced well but missing a returnable can still be set aside.
How do you measure the plans?
Trade by trade, and in the units the work is priced in. Concrete in cubic metres, walls and ceilings in square metres, skirting and edges in lineal metres, doors and fittings as a count. Each quantity should be traceable back to the drawing it came from, so you can check it later and so can anyone else. That measuring step is the take-off, and what a quantity take-off is covers it in more detail.
The measured items become your bill of quantities: one line per item, with a quantity and a unit. A good BOQ lets you send each trade's lines to the subbie for that trade and get back prices you can compare like for like. See what is in a priced bill of quantities for a real page from one.
Where do the rates come from?
From the people who will do the work. Your own crew's labour and productivity, your suppliers' prices for materials, and quotes from subbies for the trades you do not carry. Where you have no quote yet, use a rate you trust for your area and mark it as one to check.
Rates move with location, access and the size of the job, so a rate from one job is a starting point for the next, not an answer. If you have preferred supplier or subcontractor rates, we can work with those when we price for you.
What gets added on top of the measured work?
Three things. First, preliminaries: the cost of running the site rather than building any one part of it. They are easy to under price because no single drawing shows them. What preliminaries are lists what usually goes in.
Second, allowances for what cannot be priced yet. Work that is not designed is carried as a provisional sum, and items still to be selected, like tapware or tiles, as prime cost items. Provisional sums and prime cost items explains the difference and how each is adjusted later.
Third, your margin for overhead and profit. Add it once, at the end, in the way the client asked to see it. Margin buried in every rate and then added again on the total is a common way to price yourself out of a job.
What goes wrong most often?
- Pricing an old revision because an addendum came in after the take-off.
- Leaving a trade out because it sits on a drawing nobody opened, like services or external works.
- Assuming what the drawings do not show, instead of asking an RFI or listing it as an exclusion.
- Short preliminaries on a job that runs longer than planned.
- Margin added twice, or not at all.
Most of these are caught by a second person checking the estimate before it goes out. That is why every estimate we send is checked by an engineer in Australia first.
How long does pricing a tender take?
It depends on the size of the job and how complete the drawings are. A small renovation is quicker than a multi-unit job, and a multi-unit job or a commercial fit-out with a full tender pack takes longer, and the tender documents themselves add work. Most of our estimates are delivered within two working days after your go-ahead, and the date is confirmed with your fixed fee.
Should you price every tender yourself?
Not if pricing stops you from bidding. A builder or trade contractor who turns down tenders because there is no time to price them is losing work before it starts. You can hand the measuring and pricing to an estimating service, then add your margin and send the quote yourself.
A Gold Coast painting contractor had 13 tenders priced in four months, $233 each on average. Read the Rusty's Painting case study to see what the estimates looked like. Our fee is fixed per job, and a few of the fees we have charged are below.
- Granny flat, renovation, extension or shed$200 to $400
- All trades, $2.5M house$2,000
- 20 senior health units, NSW Health$1,100