How a Sydney builder went from one trial job to six priced tenders and a win
Newbuild Developments won the Cabramatta West seniors housing tender using a BOQ and marked-up plans from Constructline. It was one of six tenders we priced for them across nine months, starting from a single trial job.
- tenders priced in nine months
- 6
- from first brief to a full BOQ
- 4 days
- for all six, including GST
- $5,361.60
- confirmed by the client
- 1 win
A trial job, four days to price it
Newbuild came to us on 2 February 2026 with one job and no history with us: a BOQ for 19 seniors housing units at Lochinvar Road, Revesby, a Land and Housing Corporation project. They sent an Excel template listing the items they needed quantities for, and an invite to the tender drawings.
We sent a work-in-progress markup after one day, so they could check we were reading the plans the way they wanted. The finished BOQ and marked-up plans went out on 6 February. The scope was the whole build, not one trade: demolition, piling, bulk earthworks, formwork, reinforcement, concrete, brickwork, roofing, partitions and finishes.
"It seems that the work is heading in the right direction. Please continue your excellent efforts!"
Show the work before it is finished
On day two of Revesby, Muzammil asked how we had calculated the concrete for the piles, and we showed our working. He then asked us to confirm that 2,224 m² of R4 ceiling batts applied to Level 1 only, and to exclude patios and balconies because they have no ceilings. We revised the quantities and reissued the markup the same day.
That pattern held on every job after it: a markup early, a direct answer when a quantity was queried, and a reissued set rather than an argument. Where a drawing did not give us what we needed, we said so in the BOQ. On Panania we noted that pile length was assumed at 7 m because no geotechnical report had been provided, and flagged it as subject to revision.
One trial job became six tenders
Five days after the Revesby BOQ landed, Newbuild invited us into their next tender.
| Project | Scale | What we priced | When |
|---|---|---|---|
| Lochinvar Road, Revesby | 19 seniors housing units | Full BOQ and marked-up plans | Feb 2026 |
| Cabramatta | 20 seniors housing units | Full estimate and marked-up plans, 3 progress revisions | Feb 2026 |
| Cabramatta West | 18 seniors units | 50% and 100% submissions, then 3 further revisions | Mar to Sep 2026 |
| Cabramatta West, Ritek and Gyprock | Same site, separate trade package | Wall system and plasterboard quantities | Apr 2026 |
| Canley Heights | 18 seniors units | Brickwork BOQ, internal and face brick | Feb to Jun 2026 |
| Panania | 18 seniors units | Full BOQ, 45 trade sections | May to Jun 2026 |
The Cabramatta 20-unit job came in on 11 February with the tender close bearing down. We committed to one week, sent progress sets on 13 and 18 February, and delivered the final marked-up plans on 19 February. Cabramatta West, the one they won, ran longest. The estimate grew from 90 rows at the 50% submission in March to 198 by the final revision in September, as the drawings developed and more trades were broken out.
We found our own error and said so
In September 2026, reviewing the Cabramatta West retaining wall before the final submission, our operations manager noticed the original estimate had measured only one side of a double-brick wall. Nobody had queried it. We raised it anyway, split the wall into separate rows for each face, and reissued.
At Newbuild's own allowance of 51 bricks per square metre, the corrected area of 288 m² brought the total to 14,688 bricks. It went out as revision 5 on 24 September, a month before Newbuild confirmed the win.
What it cost
The estimating behind the winning Cabramatta West bid cost Newbuild $1,398.12, including GST. That covers the main estimate, 56 hours of estimating and senior review, and the separate Ritek and Gyprock package. All six tenders came to $5,361.60, including GST. The fees on our homepage exclude GST.
Cabramatta West is 18 seniors dwellings for the NSW Land and Housing Corporation, approved in July 2025, with a publicly reported budget of about $15 million. That figure is not Newbuild's contract sum. Against it, the estimating cost about 0.009%, or roughly 9 cents for every $1,000 of project value.
They won it
On 23 October 2026 we asked Muzammil how the Cabramatta tender had gone.
"Yes, great news! Newbuild successfully won the Cabramatta project."
He added that he would reach out next time they were tendering.
If you price seniors housing, social housing or multi-residential work, and estimating capacity limits how many tenders you can chase, this is the service.
Get a price for your jobQuantities are from the issued BOQs and fees from issued invoices, in AUD including GST. Quotes are verbatim from client emails. The $15 million is a publicly reported project budget.