What are preliminaries in a construction estimate?
Updated 13 November 2026
Preliminaries are the costs of running the job rather than building any one part of it: site setup, supervision, amenities, access, cleaning and the like. In an estimate they are priced as a trade of their own, usually the first section of the bill of quantities, and most of them grow with the time the job takes.
You will also hear them called prelims, or site overheads. They are easy to get wrong because no single drawing shows them. This guide covers what goes in them, how they are priced, why they go wrong, and how they differ from your margin.
What goes in preliminaries?
Anything the site needs to run that is not part of the finished building. The list changes with the job, but these are the usual items, and whether each one is a fixed cost or grows with time on site:
| Item | What it covers | Fixed or time |
|---|---|---|
| Site setup and removal | Fencing, hoardings, site sheds, signage and taking it all away at the end | Fixed |
| Supervision | The site supervisor or foreman, and project management time | Time |
| Amenities | Toilets, lunch rooms, power and water for the site | Time |
| Access | Scaffold, edge protection and temporary stairs | Both |
| Lifting | Cranes, hoists and the people to run them | Both |
| Cleaning and waste | Ongoing site cleans, skip bins and the final clean | Both |
| Insurance, permits and fees | Contract works insurance, permits and authority fees, where they are yours | Fixed |
| Set out and surveys | Setting out the building and any surveys the job needs | Fixed |
Some tender documents list the preliminaries they want priced, item by item. If yours do, price to that list, so your tender can be compared line for line with the others.
How are preliminaries priced?
In two parts. Fixed costs are priced once: bringing the site sheds in and taking them away, setting out, a permit. Time related costs are priced per week and multiplied by the weeks the job runs: the supervisor, the toilets, the scaffold hire, the bins.
That means you need a program before you can price preliminaries properly. Even a rough one, with how long each stage takes and when the scaffold or crane is needed, is better than a guess at the total. Where an item serves only part of the job, like a crane for the steel, price it for the weeks that stage runs, not the whole job.
How much should preliminaries be?
There is no fixed share of the job that is right. Preliminaries depend on how long the job runs, how tight the site is, how high you build and what the client asks for. A tight inner city site with a crane and a long program carries far more than a house on an open block, even if the building work costs about the same.
A rule of thumb from your past jobs is a fair way to check your total once it is priced. It is a poor way to price it in the first place, because the job in front of you is never the average.
Why do preliminaries go wrong?
- The job runs longer than the program, and every time related item runs longer with it.
- An item is left out because it sits on no drawing, like edge protection or a traffic plan.
- An item is priced twice, once in preliminaries and again in a subbie's quote, like scaffold or cleaning.
- The supervisor is left out because they are on the books anyway.
The double up is the one to watch. When subbie quotes come back, check what each one includes against your preliminaries before the tender goes in.
Are preliminaries the same as overhead and margin?
No. Preliminaries are the cost of this site: things you would not spend if you did not win the job. Overhead is the cost of running your business, like the office, the ute and the bookkeeper, spread across every job. Margin is your profit. Keep them apart in the estimate, so you can see what the job itself costs and what you are adding on top.
Preliminaries are also not the same as provisional sums, though both sit outside the measured work. A provisional sum is an allowance for work that cannot be priced yet. Provisional sums and prime cost items explains those, and how to price a tender shows where each one fits.
Do we price preliminaries for you?
Yes. Preliminaries are one of the 19 trades we price, and they come as their own section of your bill of quantities, in Excel, so you can change any line to suit how you run your sites. See what is in a priced bill of quantities for a real page from one.
A Sydney builder went from one trial job to six priced tenders and won Cabramatta West. Read the Newbuild Developments case study. Our fee is fixed per job, and a few of the fees we have charged are below.
- Granny flat, renovation, extension or shed$200 to $400
- All trades, $2.5M house$2,000
- 20 senior health units, NSW Health$1,100
Find more answers in our guides.
Get a price for your job