BOQ vs schedule of rates: what is the difference?
Updated 13 November 2026
A bill of quantities (BOQ) gives a quantity, a rate and a total for every item on the plans, so the job adds up to one price. A schedule of rates gives only the rate for each unit of work, and what you get paid depends on how many units are measured once the work is done.
So a schedule of rates tells you what a square metre of tiling costs. A BOQ tells you what the tiling on this job costs. This guide covers what each one looks like, how they compare, when a client asks for a schedule of rates instead, and how to price one.
What does a bill of quantities look like?
A BOQ is the job measured from the plans and set out trade by trade. Each line names an item, gives its quantity and unit, and carries a rate and a total. The totals add up to the trade, and the trades add up to the job. Builders use one to price a tender or a fixed price quote, and to send each trade's lines to subbies for prices.
Because every quantity is measured before the price goes in, the BOQ is only as good as the measuring under it. That measuring step is the take-off. What a quantity take-off is covers how it is done.
What does a schedule of rates look like?
A schedule of rates is a list of the kinds of work a job or a contract may need, each with a unit and a rate, and no quantity. A painting schedule might list a rate per square metre for walls, per square metre for ceilings and per door. A maintenance schedule might list rates per hour for each trade, and a rate per call out.
The client uses it when they do not know yet how much work there will be. The work is measured as it is done, or after, and paid at the rates in the schedule. Some schedules come blank from the client for you to fill in. Others come with the client's own rates and ask you to price an adjustment, up or down.
How do they compare side by side?
| Bill of quantities | Schedule of rates | |
|---|---|---|
| What each line holds | A quantity, a unit, a rate and a total | A unit and a rate, with no quantity |
| Is there a job total? | Yes, the lines add up to a price | No, the total is known only once the work is measured |
| When the quantities are known | Before the price, from the plans | As the work is done, or later |
| Who carries the quantity risk | Mostly the builder, if the price is fixed | Mostly the client |
| Where you usually see it | Tenders and fixed price quotes | Maintenance, repairs, panel work and early works |
Who carries the risk depends on the contract, not the document. Some BOQ contracts are remeasured at the end, and some schedules of rates come with a cap. Check your contract before you assume either way.
When does a client ask for a schedule of rates?
When the scope cannot be measured up front. These are the common cases:
- Maintenance and repair work across a group of buildings, where nobody knows what will break.
- A panel or period contract, where you are one of several contractors called on as work comes up.
- Early works or demolition, where what is found on site sets how much is done.
- Variations on a job, where the client wants agreed rates before the changes come.
If the drawings are complete and the client wants one number to compare tenders on, they will ask for a lump sum price, and a BOQ is how you get to it.
How do you price a schedule of rates?
Each rate has to carry everything a BOQ would spread across the job: labour, materials, plant, your share of site costs, and margin. Because you do not know how many units there will be, you also have to decide what the rate covers if the quantity is small. A rate that works on a large area can lose money on a small one, once you count travel, set up and a minimum crew.
A good way to test your rates is to price a sample job both ways. Measure a typical job into a BOQ, price it line by line, then check what your schedule rates would have charged for the same quantities. If the two are far apart, one of them is wrong.
Can you turn one into the other?
Yes, in one direction. Give a schedule of rates a set of quantities and it becomes a priced BOQ. That is what happens when the work is measured at the end. Going the other way, a priced BOQ gives you a rate for every item it measures, and those rates are a fair start for pricing variations on the same job.
What you cannot do is get a job total from a schedule of rates alone. Without quantities, there is nothing to multiply the rates by.
Which one do we write for you?
A priced bill of quantities, in an editable Excel workbook, with marked-up plans that show where each quantity came from. You can change any rate to your own and the totals follow, which also makes it a useful base if a client asks you for rates. See what is in a priced bill of quantities for a real page from one, and how to price a tender for the steps that turn it into a price.
Our fee is fixed per job, from $200 ex GST. A few of the fees we have charged:
- Granny flat, renovation, extension or shed$200 to $400
- All trades, $2.5M house$2,000
- 20 senior health units, NSW Health$1,100
The full table, and how the fee is worked out, is in what a construction estimate costs. Find more answers in our guides.
Get a priced BOQ for your job