Provisional sums and prime cost items: what goes in your estimate?
Updated 13 November 2026
A provisional sum is an allowance in your estimate for work you cannot price yet, because it is not designed or not known. A prime cost (PC) item is an allowance for something still to be chosen, like tapware or tiles, where you know the work to fit it but not the price of the item.
Both are placeholders. Each one is replaced by the real cost later, and the contract price moves up or down with it. This guide covers how they differ, how to set the amounts, what happens when the real cost comes in, and how we carry them in an estimate.
What is the difference, side by side?
| Provisional sum | Prime cost item | |
|---|---|---|
| What it allows for | Work that cannot be priced yet | An item that has not been chosen yet |
| What is unknown | The scope, the design or the conditions | The supply price of the item |
| What the allowance usually covers | Supply and install, the whole piece of work | Usually supply only, with fitting priced in your rates |
| Typical examples | Rock excavation, a lift, a facade, unknown services | Tapware, tiles, appliances, light fittings, door hardware |
| What happens later | Replaced by the actual cost once the work is known | Replaced by the actual price of the item chosen |
The short version: a provisional sum is for work you cannot measure. A PC item is for a product nobody has picked.
When should you use a provisional sum?
When a part of the job cannot be priced from the documents you have, and leaving it out would make your price look cheaper than it is. Rock in the excavation that nobody has tested for. Services under the slab that are not on any survey. A specialist package, like a lift or a facade, that is still being designed by someone else.
A provisional sum is not a place to park work you did not get time to price. If the drawings show it and you can measure it, measure it. Every provisional sum is a number the client will question, and a tender with too many of them is hard to compare and easy to pass over.
When should you use a PC item?
When the owner has not chosen a finish or a fitting yet, but you know where it goes and what it takes to install. The usual ones on a house are:
- Tapware, basins, toilets and other sanitary fixtures.
- Floor and wall tiles, priced as a supply rate per square metre.
- Kitchen appliances, like the oven, cooktop and rangehood.
- Light fittings, door hardware and other selections left to the owner.
The labour to fit each item stays in your measured rates. Only the supply price is the allowance. Say so next to each PC item, so nobody reads it as an installed price.
How do you set the amount?
Make it realistic for the job, not low enough to win it. A PC amount set below what the owner is likely to choose turns into a variation the day they pick their tiles, and a provisional sum set too low turns into a hard conversation once the work is uncovered. Both make the next tender harder to win with the same client.
For a PC item, base the amount on the standard of finish the plans and specification describe, and state the supply rate, such as a rate per square metre of tile. For a provisional sum, base it on what you know and write down what you assumed, such as the depth of rock or the length of service you allowed for. The assumption is what lets the adjustment be fair later.
What happens when the real cost comes in?
The allowance comes out and the actual cost goes in. If the owner chooses dearer tapware than the PC amount, the contract price goes up by the difference. If the rock is shallower than allowed, the price comes down.
Whether you add margin on the difference, and how much, is set by your contract. So is how the adjustment has to be shown to the owner, and in some home building contracts there are rules about how these allowances are described. Check your contract, and get advice if you are unsure. We do not give legal or contract advice.
How do we carry them in your estimate?
As their own lines in the priced bill of quantities, labelled as allowances, so you can see them and change the amounts to your own before you tender. Lifts, facades and other specialist work that is outside what we price is carried as a provisional sum, and listed as such.
Anything the drawings leave open goes on the RFI list as a question, and anything outside the price goes on the exclusions list. Between the allowances, the RFIs and the exclusions, you can see exactly where your price is firm and where it can still move. See what is in a priced bill of quantities for a real page from one, and how to price a tender for where these allowances sit among the other steps.
Provisional sums are easy to confuse with preliminaries, because both sit outside the measured work. Preliminaries are the cost of running the site. What preliminaries are covers them.
What does an estimate cost?
Our fee is fixed per job, from $200 ex GST, and agreed before we start. A few of the fees we have charged:
- Granny flat, renovation, extension or shed$200 to $400
- All trades, $2.5M house$2,000
- 20 senior health units, NSW Health$1,100
The full table, and how the fee is worked out, is in what a construction estimate costs. Find more answers in our guides.