RFIs and exclusions in a tender: what goes in each?

Updated 13 November 2026

An RFI, or request for information, is a question you send the client or their designer when the plans or specification leave something unclear, missing or in conflict. An exclusion is a line in your tender that says what your price does not cover, so nobody can assume it is in.

Both do the same job: they stop a gap in the documents becoming a cost you carry. An RFI closes the gap before you price. An exclusion fences it off when it cannot be closed in time. This guide covers when to use each, how to write them, and what to do when an answer never comes.

When should you send an RFI?

As soon as you find the gap, and before the tender closes. Most tenders set a last day for questions, often some days before the closing date, so check your tender documents for it. Common reasons to ask:

  • Two drawings disagree, like a wall that is block on the plan and framed on the section.
  • A detail is referenced but not in the set.
  • A finish or product is not specified, so there is nothing to price.
  • The scope is unclear, like whether demolition or landscaping is yours.

On many tenders the answer goes to every tenderer as an addendum, so asking does not give your price away. It does make sure everyone prices the same thing.

How do you write a good RFI?

Make it easy to answer in one line. Ask one question per RFI, and name the drawing number and revision it comes from. Say what you have assumed, so a quiet reply still leaves a record. "Footing F3 on S-02 rev B has no size. We have assumed it matches F2. Please confirm" gets an answer faster than "Please clarify the footings".

Keep a list with the date each one was sent and answered. When an answer arrives, check it against your quantities, because it may change more than the one line you asked about.

What if the RFI is not answered before the tender closes?

Price it anyway, on a stated assumption, and say so in your tender. You have three ways to do that. Price it as you assumed and list the assumption as a clarification. Carry a provisional sum for it, if it is work that cannot be measured yet. Or exclude it outright, if it is something you will not price at all. Provisional sums and prime cost items explains how allowances are adjusted later.

What happens if your assumption turns out wrong depends on your contract, so check your contract before you rely on it.

What goes on an exclusions list?

Anything a reasonable client might think is in your price but is not. Every job is different, but these come up often:

Common exclusion Why it is often left out
Authority fees and charges Set by council or the utility, and often not known until approval
Rock or contaminated soil Nobody knows what is under the ground until it is dug
Work outside the boundary Footpaths, crossovers and service connections the plans do not show
Owner supplied items The client is buying them, so only the install is in your price
Out of hours work Priced at normal hours unless the tender asks otherwise
Design and certification Your price is to build the design, not to change or certify it

Write each exclusion so it cannot be read two ways. "Rock excavation" is clearer than "site conditions". And only exclude what you mean to: an item that is in your price but also on your exclusions list confuses everyone.

Can too many exclusions cost you the tender?

Yes. A client comparing tenders will add back what you left out, often at a figure worse than yours. A long list of exclusions can also read as a builder who did not look closely. Exclude what you genuinely cannot price, and answer the rest with an RFI, an assumption or an allowance. Some tenders ask you to price on their documents without qualifications at all, so check the tender conditions.

Are exclusions the same as returnables?

No. Returnables are the forms and schedules the tender asks you to fill in and send back with your price, like the pricing schedule, insurances or a program. Your exclusions and clarifications usually go in with them, but they are your own list. How to price a tender shows where each one fits.

Do we write the RFI and exclusions lists for you?

Yes. Exclusions & RFIs come with the estimate as an Excel list: see what sits outside the price and what needs an answer. You review them, send the questions you want answered, and put the exclusions in your tender. These are jobs we have priced that came with them:

  • All trades, $2.5M house$2,000Excel BOQ, marked-up plans, the exclusions list and the RFI list.
  • 20 senior health units, NSW Health$1,100Every trade across all 20 units. Excel BOQ, marked-up plans and the RFI list.

See tender estimating for what else comes with a tender pack. Before you send the plans, read what to send an estimator, and look up any unfamiliar term in the estimating glossary. Find more answers in our guides.